The following scheduled roadwork has been verified at the time of release. Please keep in mind work is weather permitting and subject to change.For updates to this list, visit: QuickMap at http://quickmap.dot.ca.gov, check the California Highway Information Network (CHIN) at https://roads.dot.ca.gov or call 1-800-GAS-ROAD (1-800-427-7623). For information pertaining to emergency roadwork, check QuickMap and the CHIN. 

Del Norte County

  • U.S. 101 (0/3.8) – Utility work is scheduled between Humboldt County Line and Klamath Beach Road weekdays from 7 a.m. to 7 p.m. Lane and shoulder closures will be in effect. Travelers should expect minor slowdowns. LC#C101XC
  • U.S. 101 (3.8/4.6) – K-Rail installation is scheduled between Klamath River Overflow Bridge 1-32 and Route 101/169 Separation 1-26 weekdays from 7 a.m. to 5 p.m. One-way traffic control will be in effect. Travelers should expect 5-minute delays. LC#C101CA
  • U.S. 101 (8.2/9.4) – K-Rail installation is scheduled between Requa Rd – Minot Creek Rd and High Prairie Creek Bridge 1-04 weekdays from 7 a.m. to 5 p.m. One-way traffic control will be in effect. Travelers should expect 5-minute delays. LC#C101CA
  • U.S. 101 (35.8/36.5) – The Dr. Fine Bridge Replacement Project is scheduled in the Smith River area weekdays from 7 a.m. to 7 p.m. One-way traffic control will be in effect. Travelers should expect 10-minute delays. LC#C101WA

Humboldt County

  • Route 36 (4.1/4.6) – Construction upgrades near Carlotta are scheduled to continue. One-way traffic control will be in effect. Travelers should expect up to 15-minute delays weekdays from 7 a.m. to 7 p.m. LC#C36IA
  • Route 36 (15.7/16.3) – Slide response west of Grizzly Creek Redwoods State Park will continue. One-way traffic control will continue with delays of up to 15 minutes. Check Caltrans District 1 on social media for updates. LC#T36HA
  • Route 36 (19.6) – Emergency work west of Maple Grove will continue. One-way traffic control will be in effect. Travelers should expect up to 5-minute delays. LC#C36JA
  • Route 36 (29.2) – Utility work is scheduled near Deerfield Ranch Rd on Thursday, April 2 from 7 a.m. to 6 p.m. One-way traffic control will be in effect. Travelers should expect 5-minute delays. LC#P36BA
  • Route 36 (34.5) – Bridge work at Butte Creek Bridge 4-116 is scheduled to continue. One-way traffic control will be in effect. Travelers should expect 5-minute delays. LC#C36UA
  • Route 96 (3.2/4.7) – Utility work is scheduled between Pipeline Overcrossing and Turnout at Postmile 4.65 on Friday, March 27 from 7 a.m. to 3 p.m. One-way traffic control will be in effect. Travelers should expect 10-minute delays. LC#C96BA
  • Route 96 (7.5/8.1) – Emergency work is scheduled between 0.5 mile west of Tish Tang Campground and Tish Tang Campground. One-way traffic control will be in effect. Travelers should expect 5-minute delays. LC#C96IA
  • Route 96 (10.1/15.4) – Utility work is scheduled between Trinity River Elders Village and Mill Creek Road weekdays from 7 a.m. to 7 p.m. One-way traffic control will be in effect. Travelers should expect 10-minute delays. LC#C96BA
  • Route 96 (10.2/15.4) – Utility work is scheduled between North Shoemaker Ditch and Mill Creek Road weekdays from 7 a.m. to 7 p.m. One-way traffic control will be in effect. Travelers should expect 10-minute delays. LC#C96BA
  • Route 96 (11/12.1) – Utility work is scheduled between Loop Road and River Road weekdays from 7 a.m. to 7 p.m. One-way traffic control will be in effect. Travelers should expect 10-minute delays. LC#C96BA
  • U.S. 101 (33.8/34.3) – Emergency work will continue between 0.8 mi South of Federation Grove Separation 4-114 and 1.3 mi South of Federation Grove Separation 4-114. Lane closures will be in effect. Expect minor traffic slowdowns. LC#C101VC
  • U.S. 101 (51.8/52.6) – Bridge inspection is scheduled between Davis Street Overcrossing 4-237 and Scotia Separation 4-234 on Wednesday, April 1 from 7 a.m. to 5 p.m. Lane and shoulder closures will be in effect. Expect minor traffic slowdowns. LC#C101NE
  • U.S. 101 (53.4/54.6) – Bridge work will continue between Metropolitan Heights Road and Scenic Way Undercrossing 4-235. Lane and shoulder closures will be in effect. Expect minor traffic slowdowns. LC#C101NE
  • U.S. 101 (60.7/62.2) – Bridge inspection is scheduled between Rohner Creek Bridge 4-108 and Palmer Blvd Undercrossing 4-112 on Tuesday, March 31 from 7 a.m. to 5 p.m. Lane and shoulder closures will be in effect. Expect minor traffic slowdowns. LC#C101NE
  • U.S. 101 (68.2/70.6) – Bridge inspection is scheduled between Hookton Road Overcrossing 4-166 and Tompkins Hill Rd Overhead Bridge 4-121 on Wednesday, April 1 from 7 a.m. to 5 p.m. Lane and shoulder closures will be in effect. Expect minor traffic slowdowns. LC#C101NE
  • U.S. 101 (80.3/81.4) – Electrical work is scheduled between Cole and Jacobs Avenue and the Mid City Motor World Entrance on Thursday and Friday, March 26 and 27, overnight from 8 p.m. to 6 a.m. Lane and shoulder closures will be in effect. Expect minor traffic slowdowns. LC#C101FD
  • U.S. 101 (82.7) – Work is scheduled north of Eureka near the Indianola Cutoff. Access to southbound 101 from Indianola Cutoff remains closed. Use an alternate route and expect minor traffic slowdowns. LC#C101FD
  • U.S. 101 (114.5/116.9) – Sign work is scheduled between McDonald Creek Road, Dry Lagoon, and Old State Hwy on Friday, March 27 from 7 a.m. to 3 p.m. One-way traffic control will be in effect. Expect 5-minute delays. LC#C101GE
  • Route 169 (25.8/30.2) – Utility work is scheduled between Coon Creek Bridge 4-219 and Martins Ferry. One-way traffic control is scheduled weekdays from 7 a.m. to 5 p.m. Travelers should expect delays of up to 15 minutes. LC#C169CA
  • Route 169 (31.1/32.1) – Tree work is scheduled between Refuse Disposal Road and Spey-Gee Point Lane on Friday, March 27 from 7 a.m. to 5 p.m. One-way traffic control will be in effect. Travelers should expect 5-minute delays. LC#P169BA
  • Route 254 (18.8) – Slide removal work is ongoing just north of Weott. One-way traffic control will be in effect. Motorists should expect 5-minute delays. LC#C254AA
  • Route 299 (31.7) – A right shoulder closure remains in effect near 1.1 mile east of Cedar Creek Road in the Willow Creek area due to emergency work. Expect minor traffic slowdowns. LC#T299GA
  • Route 299 (32.1/32.5) – Work is scheduled west of East Fork Willow Creek Bridge 4-115 on weekdays from 7 a.m. to 5 p.m. One-way traffic control will be in effect. Travelers should expect 10-minute delays. LC#C299LA

Lake County

  • Route 20 (16.6/18.1) – Electrical work in Lucerne from Grove Street to Ogden Road will begin on Thursday, March 26. One-way traffic control will be in effect from 9 p.m. to 6 a.m. Motorists should anticipate up to 10-minute delays. LC#C20TA
  • Route 29 (5.9) – Traffic signal work in Middletown at Wardlaw Street will continue. Lane closures will be in effect from 9 p.m. to 6 a.m. Motorists should expect up to 5-minute delays. LC#C29QA

Mendocino County

  • Route 1 (30.6/31.3) – Emergency work south of Elk continues. One-way traffic control will be in effect and motorists should anticipate up to 10-minute delays. LC#T1BA
  • Route 1 (62.3/62.8) – Utility work in Fort Bragg from the Pudding Creek Beach Access to Airport Road will conclude on Friday, March 27. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should expect up to 5-minute delays. LC#P1DA
  • Route 1 (75.9/76.2) – Emergency work south of Westport from the Blues Beach Trailhead to the Overlook will continue. One-way traffic control will be in effect from 7 a.m. to 6 p.m. Motorists should anticipate up to 30-minute delays. LC#C1TA
  • Route 1 (78.1/78.4) – Emergency work in Westport at Wages Creek Road continues. One-way traffic control will be in effect from 10 a.m. to 7 p.m. Motorists should anticipate up to 10-minute delays. LC#C1BB
  • Route 1 (82.5/82.9) – Culvert work from north of Hillshore Drive to the Juan Creek Bridge 10-140 continues. One-way traffic control will be in effect from 7 a.m. to 8 p.m. Motorists should expect up to 5-minute delays. LC#C1CB
  • Route 20 (1.4/3.5) – Utility work will begin in Fort Bragg from Pine Tree Lane to east of Walters Lane on Monday, March 23. One-way traffic control will be in effect from 8:00 a.m. to 7:30 p.m. Motorists should expect up to 5-minute delays. LC#C20UA
  • Route 20 (14.1/17.1) – Road work will occur at various locations from Three Chop Road to the Camp 20 Recreation Area on Friday, March 27. One-way traffic control will be in effect from 9:00 a.m. to 2:30 p.m. Motorists should anticipate up to 10-minute delays. LC#H20BA
  • Route 20 (33.1/33.2) – Culvert work in Willits from South Street to Walnut Street will continue. Westbound lane closures will be in effect from 8:30 a.m. to 4:30 p.m. and motorists should expect minor slowdowns. LC#P20DA
  • U.S. 101 (4/5.1) – Emergency work from the Frog Woman Rock State Historic Landmark to the Comminsky Station Road Viaduct 10-289 continues. Lane closures will be in effect from 7 a.m. to 5 p.m. Motorists should expect minor slowdowns. LC#C101VA
  • U.S. 101 (10.6/11) – Utility work in Hopland from the Feliz Creek Bridge 10-3 to First Street continues. One-way traffic control will be in effect from 8 p.m. to 6 a.m. Motorists should anticipate up to 10-minute delays. LC#C101JD
  • U.S. 101 (10.6/10.8) – Utility work in Hopland from the Feliz Creek Bridge 10-3 to Mountain House Road will begin on Monday, March 23. Southbound lane closures will be in effect from 9 a.m. to 3 p.m. Motorists should expect minor slowdowns in the area. LC#P101IA
  • U.S. 101 (12/13.2) – Utility work from the Cal Fire Hopland Fire Station to Road 112A will occur on Thursday, April 2. One-way traffic control will be in effect from 7 p.m. to 12 a.m. Motorists should expect up to 5-minute delays. LC#P101IA
  • U.S. 101 (13.7/59.5) – Utility work at various locations from north of the Crawford Creek Bridge 10-168 to Route 162 continues with lane closures and minor slowdowns. Weeknight northbound ramp closures will occur in Ukiah at Talmage Road and Rivino Ranch Road. Motorists should use an alternate route. LC#C101KE
  • U.S. 101 (50.8/51.5) – Construction work near Schow Road continues. Lane closures will be in effect from 7 a.m. to 3 p.m. and motorists should expect minor slowdowns. LC#C101GA
  • U.S. 101 (72.1/72.7) – Emergency work north of Laytonville at Woodruff Drive continues. Lane closures will be in effect and motorists should anticipate up to 15-minute delays. LC#T101GA
  • U.S. 101 (86.5/87.5) – Emergency work south of Leggett continues. Lane closures will be in effect and motorists should expect up to 5-minute delays. LC#T101GA
  • Route 128 (0.1) – Road work at Jct Route 1 will begin on Friday, March 27. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should anticipate up to 10-minute delays. LC#C128JA
  • Route 128 (11.5/11.6) – Road work from Flynn Creek Road to Navarro Ridge Road will begin on Monday, March 23. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should anticipate up to 10-minute delays. LC#C128JA
  • Route 162 (7.9/8.4) – Bridge work at the Eel River Bridge 10-236 continues. Lane closures will be in effect and motorists should expect up to 10-minute delays. LC#C162HA
  • Route 162 (14.5/15.2) – Utility work will occur from west of the Middle Fork Eel River Bridge 10-252 to Laytonville Dos Rios Road on Friday, March 27. One-way traffic control will be in effect from 7 a.m. to 4 p.m. Motorists should expect up to 5-minute delays. LC#P162DA

*Items in bold indicate updates from the previous week.

# # #

Facebooktwitterpinterestmail

Join the discussion! For rules visit: https://kymkemp.com/commenting-rules

Comments system how-to: https://wpdiscuz.com/community/postid/10599/

Subscribe
Notify of
guest

This site uses Akismet to reduce spam. Learn how your comment data is processed.

0 Please improve the conversation by disagreeing thoughtfully and backing your claims with facts
Oldest
Newest Most Voted
Inline Feedbacks
View all comments