Arcata’s Street Resurfacing Project Begins Tomorrow
This is a press release from the City of Arcata:
Construction for the 2020 Street Resurfacing (Slurry Seal) Project will now begin on Monday, August 10.
The City of Arcata has contracted with Dryco Construction Co., for this project, and work involves laying slurry seal and striping on the recently repaired pavement surfaces on 11 th Street, Stromberg Avenue, Stewart Avenue, Roberts Way, Wyatt Lane, 27 th Street, Hilfiker Drive, Maple Lane, Baldwin Street, Davis Way, Cropley Way, Acheson Way, Chestnut Place, Madrone Way, Valley West Boulevard and Valley East Boulevard.
Construction for this project will take place Tuesday through Saturday from 8 a.m. to 5 p.m., and on some days the contractor will extend work hours from 7 a.m. to 6 p.m.
Extensive slurry work on sections of 11 th Street is scheduled for Monday, August 10, through Thursday, August 13, and individuals driving in the area are encouraged to take alternative routes on those days.
On the days of scheduled work, members of the community are encouraged to follow all directions and traffic control devices within the project area.
Construction for the project is scheduled to be completed by Tuesday, August 25. If challenges arise with this project, please contact Dryco Construction Co. at (916) 548-5567 or the City of Arcata at (707)825-2173.
For updates on construction progress and additional City project plans, please visit cityofarcata.org.